How do you calculate safety stock and the reorder point?

Reviewed on November 16, 20265 min read

Short answer

The reorder point is the stock level at which you need to order more. You calculate it by multiplying your average daily sales by the days the replenishment takes to arrive and adding safety stock. Safety stock is the reserve that covers higher-than-normal sales or a supplier delay. Both are calculated per product and reviewed when sales or lead time change.

Key points

  • Reorder point = average daily sales x lead time + safety stock.
  • Safety stock covers two risks: selling more than expected and a late replenishment.
  • It is calculated per product, not for the whole catalog.
  • Recalculate before every peak date and when you change supplier.

The concepts you need

Basic inventory replenishment concepts
ConceptWhat it is
Average daily salesUnits sold in a period divided by the days in that period.
Lead timeDays between placing the order with the supplier and the stock being available to sell.
Safety stockA reserve to cover higher-than-expected sales or a late replenishment.
Reorder pointThe stock level at which a new order has to be placed.
Days of coverDays the current stock lasts at the average sales rate.
StockoutThe moment a product runs out and cannot be sold.

Lead time includes the time the warehouse takes to receive and locate the goods, not just the trip from the supplier.

The formulas, with an example

Safety stock = (maximum daily sales x maximum lead time) − (average daily sales x average lead time)

Reorder point = average daily sales x average lead time + safety stock

Days of cover = available stock ÷ average daily sales

Example calculation for one product
DataExample value
Average daily sales20 units
Maximum daily sales35 units
Average lead time10 days
Maximum lead time15 days
Safety stock(35 x 15) − (20 x 10) = 325 units
Reorder point(20 x 10) + 325 = 525 units
The numbers are made up to show the calculation. Use your product's.

In the example, when stock drops to 525 units it is time to order. This method is conservative: it assumes the highest sales and the longest lead time happen at the same time.

A finer method: service level

If you have your daily sales history, you can calculate safety stock from the real variation in your sales and the service level you want to offer. Service level is the probability of not running out of stock while the replenishment is on its way.

Safety stock = Z x standard deviation of daily sales x square root of the lead time in days

This version assumes lead time does not vary. If it varies a lot, use the previous method or add margin days.

Z value by service level
Service levelZ value
90%1.28
95%1.65
99%2.33
Values from the standard normal distribution.

Example: with a standard deviation of 6 units a day, a 10-day lead time and a 95% service level, safety stock is 1.65 x 6 x 3.16 = 32 units, rounding up.

Not every product deserves the same reserve

  • A products. The few that concentrate most of your sales. High service level and weekly review.
  • B products. Medium sales. Review every two weeks or monthly.
  • C products. Low or irregular sales. A small reserve, or sell to order.
  • Products with an expiry date. The reserve has a ceiling: what you can sell before the date.
  • New products. With no history, start from a similar product and adjust after a few weeks.

How to define your reorder points

  1. Export your sales by product

    At least three months, day by day, leaving out the days the product was out of stock.

  2. Measure each supplier's real lead time

    From the purchase order until the stock was available, over the latest replenishments.

  3. Classify your products

    Sort them by sales and separate A, B and C.

  4. Calculate safety stock and reorder point

    With one of the two formulas, product by product, starting with the A group.

  5. Load the reorder point as minimum stock

    In your system or your spreadsheet, so it alerts you when a product reaches that level.

  6. Review every month

    And before every event, supplier change or change of season.

If you do not have a system yet, the stock control spreadsheet lets you record the minimum stock per product.

Several channels and peak dates

  • A single stock for all channels. If each channel has its own reserve, you need more total stock. The guide on connecting your sales channels explains how to sync it.
  • Separate stock in a marketplace. What you send to a marketplace's warehouse is not available for your own store. Calculate its reorder point separately.
  • Events. Before a Cyber event, use the daily sales of the previous event and not the yearly average. The guide on how to prepare your logistics for Cyber events and Christmas has the calendar.

Frequently asked questions

What is safety stock?

It is the reserve of units you keep to cover higher-than-expected sales or a late replenishment. It prevents you from running out while the next order arrives.

How is the reorder point calculated?

Multiply your average daily sales by the days the replenishment takes and add safety stock. With 20 units a day, a 10-day lead time and a 325-unit reserve, the reorder point is 525 units.

How much safety stock should I hold?

It depends on how much your sales vary, how late your supplier tends to be and the service level you want to offer. There is no single number: it is calculated per product with one of the formulas in this guide.

How often should I recalculate?

Once a month for your best-selling products, and always before an event, a change of season or a change of supplier.

What is a stockout?

It is the moment a product runs out and is no longer available for sale. Every day without stock is a sale that does not happen.